3. Installing the Appliance¶
Before installing the appliance, make sure you have the following:
- 3U of server rack space,
- at least ten free 1/10 GbE ports in a network switch (10 GbE recommended),
- at least ten RJ45-to-RJ45 patch cables to connect the appliance to the switch,
- at least six free 1 GbE ports in a network switch for out-of-band management,
- two power sockets.
To install the appliance, perform the following steps:
- Unpack the appliance.
- Mount the appliance into rack and connect cables.
- Configure the appliance using the wizard.
- Log in to the admin panel and install a license.
- Set up the desired workload in the admin panel.
These major steps are described in more detail in the following sections.